Contract for Pihl UK

Aberdeen 3 R`s Project
Beacon Centre

Greentech are constructing 2 new Football Pitches including running track at this Contract.
We started at the beginning of February re-shaping the levels, moving 2000 cubic metres of soil, installing main drains, and around 1200 metres of Lateral Drains.
We have made excellent progress despite the inclement weather and are now at the stage of installing 14,000 metres of Sand Slits and seeding out the new pitches.